Hartford Stadium Insurer Already Wants to Get Repaid

Ryan Caron King
/
WNPR
An aerial view of the stadium from earlier this summer.

The insurance company that will pay to finish Hartford’s minor league baseball stadium is already fighting to get its money back. Arch Insurance is demanding nearly $19 million from the developer and at least one other company. 

Surety companies aren’t in the business of losing money.

“They charge a premium, as an insurance company would, for issuing a bond or bonds," said attorney Steven Kaplan, who practices construction and surety law. “However, unlike an insurance company, their agreements require that they basically lose no money. So if they have to pay money on claims, whether it’s to an owner under a performance bond or to subcontractors under a payment bond claim, they’re supposed to get reimbursed.”

The question now is, by whom?

An attorney for the stadium’s ousted developer, Centerplan, said the insurance company has already made a demand for nearly $19 million of it and its chief Bob Landino.

But according to federal court documents, Arch is also going after another company -- Greenskies Renewable Energy -- a Middletown-based solar company.

But why would an energy company be on the hook?

It’s complicated. But it goes like this. According to a lawsuit filed by Greenskies to stop the action, Landino is a member of the company. And in the course of getting bonding from Arch Insurance for the energy company, Landino signed a document that obligated him and Centerplan to cover Greenskies’ losses. That’s not unusual.

What is unusual is this: Arch Insurance claims that same document obligates Greenskies and its members to cover Centerplan’s losses, too -- including more than $18 million for the stalled stadium project.

Steven Kaplan said he hasn’t seen anything like this before.

"Not that that couldn’t happen," he said. "But it’s certainly extraordinary."

Arch declined to comment. Greenskies did not respond. And Centerplan’s attorney said he’s working to resolve the matter.

Jeff Cohen started in newspapers in 2001 and joined Connecticut Public in 2010, where he worked as a reporter and fill-in host. In 2017, he was named news director. Then, in 2022, he became a senior enterprise reporter.

Stand up for civility

This news story is funded in large part by Connecticut Public’s Members — listeners, viewers, and readers like you who value fact-based journalism and trustworthy information.

We hope their support inspires you to donate so that we can continue telling stories that inform, educate, and inspire you and your neighbors. As a community-supported public media service, Connecticut Public has relied on donor support for more than 50 years.

Your donation today will allow us to continue this work on your behalf. Give today at any amount and join the 50,000 members who are building a better—and more civil—Connecticut to live, work, and play.

Related Content